Saturday, August 28, 2010

We have a roof!











All the roof tiles have put up now, bricks have been delivered so on to the next stage. hopefully we have chosen the right colour brick, fingers crossed we will hopeful see soon.

Thursday, August 19, 2010

Frame finished. Next..





Frames all finished. Had a frame inspection yesterday with the SS and is all good. Next week we should be starting with the guttering and roof tiles will go up.

Sunday, August 15, 2010

2nd floor frame is up.







Can't believe they have done some work this week as the weather has been really bad. But they have managed to put in all the windows on the bottom floor. They have also put down the floor for the second storey and are half way finishing with second floor framing so soon they should be starting on the roof.

Saturday, August 7, 2010

Frames




Frames for the first floor has been finished, looks like a bit of a mess at the moment just wood and mud everywhere and next door neighbour has started to build too.